Wednesday, April 20, 2011

April 16-19 Work Project


About 20 volunteers came out for this four day project in Section E this weekend. A larger work crew worked the weekend to complete the brushing and treading to Horse Camp, on Monday a smaller crew built a support wall around a wide rock obstacle above Upper Shake Campground, and Tuesday saw them brushing behind the sag pond in Pine Canyon. Dick and Blair provided packer support for the saws and heavier equipment, and cleared the trail of several blowdowns. We also re-marked the route down to the spring from Horse Camp, as several large blowdowns obliterated the previously used route. The owners of Rancho Corona del Valle just down the road were our generous overnight hosts, and Doris was our cook. Congrats and BIG THANKS to all.